The Company plans to set up an LNG Receiving and Regasification
Terminal at Kochi (Kerala) for 2.5 MMTPA nominal capacity which
is equivalent to 10 MMSCMD of natural gas with provision of expansion
up to 5 MMTPA. The Government of Kerala have shown keenness to have
equity in the Kochi Terminal. Kochi Port Trust has allocated 40
Ha. of land at Puthu Vypeen Island for the development of LNG Terminal
which includes construction of Jetty and Breakwater.
Storage and Regasification facilities will include unloading arms,
two tanks of 110,000 cu.m capacity each, vaporization system and
utilities and off-site facilities. The estimated cost of the project
is Rs. 2,000 crores.
The Company has identified consumers in and around Kochi for utilization
of regasified LNG. All the pre-project activities including various
on-shore and off-shore surveys / investigations, preparation of
Detailed Feasibility Report and Basic Engineering Package, Mathematical
and Physical Modeling Studies, Terrestrial and Marine Environment
Impact Assessment Studies have been completed.
The Company has received Environment Clearance from the Ministry
of Environment & Forest, New Delhi.